Houses for all under Pradhan Mantri Awas Yojana – Gramin

0
504

In order to achieve the target of “Housing for All” in rural areas, the Ministry of Rural Development is implementing Pradhan Mantri Awaas Yojana- Gramin (PMAY-G) with effect from 1st April, 2016 to provide assistance to construct 2.95 crore pucca houses with basic amenities. The initial timeline for PMAY-G was 2022, which has now been extended to March, 2024. Out of the overall target of 2.95 crore houses, a target of 2.92 crore houses had been allocated to States/Union Territories UTs), out of which, 2.49 crore houses have been sanctioned to beneficiaries by various States/UTs and 2.10 crore houses have been completed as on 07.12.2022.

The targets under PMAY-G are set annually on the basis of availability of eligible beneficiaries, achievements of targets allocated during the preceding years, discussions held with States/UTs during Annual Action Plan and proposal of the State/UT. After allocation of annual targets, further distribution of targets among beneficiaries in various districts/blocks/villages is done by the States/UTs on the basis of eligible number of beneficiaries in the Permanent Wait List (PWL)/finalized Awaas+ list.

Under the PMAY-G, there is a grievance redressal mechanism set up at different levels of administration viz., Gram Panchayat, Block, District and the State. An official of the State Government is to be designated at each level to ensure disposal of grievances to the satisfaction of the complainant. The official who is designated at each level is responsible for disposing off the grievance / complaint within a period of 15 days from the date of receipt of the grievance / complaint.

The cases of irregularities reported by the Hon’ble Members of Parliament, Members of State Assembly and general public are taken up with the State Government for comments and for taking necessary action.

There is also a procedure of lodging of complaints on the Centralized Public Grievance Redress and Monitoring System (CPGRAMS) portal (pgportal.gov.in) by the public. The complaints received in the Ministry of Rural Development through CPGRAMS or otherwise are forwarded to the respective State Governments/ Union Territory (Union Territory) Administrations for redressal of the grievance.

Since inception of PMAY-G i.e. 01.04.2016 till 08.12.2022, a total of 1,451 complaints relating to irregularities in implementation of PMAY-G have been received in the Ministry of Rural Development on CPGRAMS. As the State Govt. implements PMAY-G, these complaints have been forwarded to the State for taking necessary action under intimation to this Ministry. Out of 1,451 complaints, 1,413 have been disposed-off.

The details of house target and house completion from the year 2016-17 to 2021-22 under PMAY-G and Central share released are given as under: –

 

(units in no. & Rs. in crore)

Financial Year Target allocated by the Ministry House completion Central Share released
2016-17 42,25,992 2,115 16,058.00
2017-18 31,50,162 38,15,953 29,889.86
2018-19 25,12,968 44,72,392 29,331.06
2019-20 57,95,150 21,28,843 27,305.84
2020-21 43,33,166 33,99,499 36,857.93
2021-22 71,50,439 42,39,483 26,237.24
2022-23 20,97,151 26,99,377 17,497.90

 

Under PMAY-G, the minimum size of a house is 25 square meter, including a dedicated area for hygienic cooking.

The State-wise details of the targets allocated, houses sanctioned and the houses completed under the PMAY-G is given below-

 

(units in Nos.)

Sl.No. Name of the State/UT Target allocated by the Ministry Houses

sanctioned by the States/UTs

Houses Completed
1 Arunachal Pradesh 38,384 35,987 9,818
2 Assam 20,84,070 14,57,835 7,03,332
3 Bihar 38,62,734 36,95,888 33,47,538
4 Chhattisgarh 11,76,150 10,97,095 8,28,912
5 Goa 1,707 248 140
6 Gujarat 4,49,167 4,32,860 3,99,237
7 Haryana 30,789 28,242 22,566
8 Himachal Pradesh 15,483 15,383 11,195
9 Jammu And Kashmir 2,01,633 1,95,263 1,13,314
10 Jharkhand 16,03,268 15,82,899 14,14,178
11 Kerala 42,212 34,877 24,597
12 Madhya Pradesh 37,89,400 37,54,566 30,87,221
13 Maharashtra 15,05,983 12,98,862 9,37,228
14 Manipur 46,166 36,454 18,470
15 Meghalaya 80,848 65,155 34,327
16 Mizoram 20,518 18,373 6,167
17 Nagaland 24,775 22,351 5,235
18 Odisha 26,95,837 18,36,350 17,13,224
19 Punjab 41,117 38,680 24,506
20 Rajasthan 17,33,959 17,24,373 15,42,723
21 Sikkim 1,409 1,371 1,087
22 Tamil Nadu 8,17,439 7,61,286 4,59,702
23 Tripura 2,82,238 2,49,020 1,98,662
24 Uttar Pradesh 34,78,718 26,49,795 25,95,313
25 Uttarakhand 47,654 31,649 27,514
26 West Bengal 46,18,847 34,68,683 33,88,963
27 Andaman And Nicobar 1,631 1,347 1,168
28 Dadra And Nagar Haveli

Daman and Diu

6,899 5,633 2,926
29 Lakshadweep 53 53 44
30 Puducherry*
31 Andhra Pradesh 2,56,270 1,78,865 46,726
32 Karnataka 3,07,746 1,61,873 1,01,676
33 Telangana*
34 Ladakh 1,992 1,906 1,429
  Total 2,92,65,028 2,48,83,175 2,10,69,138

* Puducherry and Telengana are not implementing PMAY-G

The State/UT-wise and category-wise details of the total number of houses allotted to the SC and ST beneficiaries is given below-

(units in Nos.)

Sl.No Name of the State/UT Houses sanctioned Houses completed
ST SC ST SC
1 Arunachal Pradesh 34,408 0 9,355 0
2 Assam 1,89,484 110714 98728 46150
3 Bihar 98,558 7,31,105 81,640 5,84,679
4 Chhattisgarh 442968 2,13,087 3,15,974 1,69,701
5 Goa 80 12 59 4
6 Gujarat 2,04,499 25,963 1,90,840 22,353
7 Haryana 127 13,889 56 9,985
8 Himachal Pradesh 2,204 5,941 1,647 4,061
9 Jammu And Kashmir 72,489 24,702 34,488 13,070
10 Jharkhand 5,35,446 2,83,068 4,57,895 2,29,254
11 Kerala 2,907 11,728 1,467 6,749
12 Madhya Pradesh 14,15,713 6,68,545 11,43,618 5,42,833
13 Maharashtra 4,17,372 1,99,619 2,97,888 1,15,713
14 Manipur 23,496 1,135 10,946 459
15 Meghalaya 60,509 365 32,692 143
16 Mizoram 18,293 15 6,155 0
17 Nagaland 22,051 1 5,076 0
18 Odisha 6,30,369 3,29,767 5,89,314 3,00,728
19 Punjab 125 27,861 19 18,750
20 Rajasthan 6,23,262 3,81,524 5,38,856 3,14,140
21 Sikkim 641 138 480 82
22 Tamil Nadu 25,803 3,47,804 17,577 1,85,016
23 Tripura 1,09,498 47,009 82,802 32,480
24 Uttar Pradesh 48,845 11,82,778 45,984 11,53,182
25 Uttarakhand 2,641 13,978 2,346 11,529
26 West Bengal 3,20,344 10,61,583 3,07,022 10,42,957
27 Andaman And Nicobar 11 0 8 0
28 Dadra And Nagar Haveli

Daman And Diu

5,552 8 2,887 3
29 Lakshadweep 45 0 45 0
30 Puducherry*
31 Andhra Pradesh 36,956 65,879 7,100 13,151
31 Karnataka 27,614 43,228 20,447 31,785
33 Telangana*
34 Ladakh 1,899 0 1,422 0
  Total 53,74,209 57,91,446 43,04,833 48,48,957

* Puducherry and Telengana are not implementing PMAY-G.

This information was given by the Union Minister of State for Rural Development, Sadhvi Niranjan Jyoti in a written reply in Lok Sabha